The cost may need to be
subtracted from the activity expense line (reduce budgeted cost and remaining
cost of the expense item) by the project team. Afterwards the project will need
to be summarized and then re-baselined to update activity data and account for
the new reduced expense cost.
This is a case where they allocate a sum of money for the
fiscal year for all things operational support and version upgrades to IT
systems, and if they decide to do an upgrade or more throughout the year, then
they create a new project for the estimated amount and they subtract money from
the original bucket (SS operations project).