The BL Project Finish date is the latest finish date of the baseline currently assigned to the project. The baseline is a snapshot in time of the project. If the dates in the activities at the time of baseline creation were not correct, the Baseline Project Finish date will not be accurate as the field is only pulling data from the baseline project data.