Monday, January 5, 2015

How to have resources loaded to the WBS Summary level activity



Add the activity, change it to a WBS Summary activity and make the duration type “Fixed Units”.
Activity Type: WBS Summary Duration Type: Fixed Units % Complete: Duration.

Load Resources to WBS Summary Activity.

No comments:

Post a Comment