This can be achieved in several ways. One method is using the progress
spotlight feature from the toolbar. Choose View, Progress Spotlight, or click
the Progress Spotlight icon to add a time period equal to the smallest
increment of the displayed timescale from the previous data date. The Project
Management module spotlights activities that should have started, progressed,
or finished between the previous data date and the new data date in the Gantt
Chart.