Is it OK to mark activities that are yet to be baselined with Actual Start date and Actual Finish date?


Activities with actual start and finish dates will become the baselined dates once we have set the baseline. Primavera will recognize the activities have been marked with actuals, so there is no reason for a “planned” or “baseline” date for this activities since we have actuals. As for charging time to these activities,