Remaining Units/Time Does Not Import Correctly From Excel For New Resource Assignment

Solution

There are three ways to work around this functionality. These changes should be made prior to importing the XLS file. The options listed below can be found under Enterprise, Projects, Calculations tab.

Change the setting under 'Link Budget and At Completion for Not Started Activities' from 'Reset Remaining Duration and Units to Original' to 'Reset Original Duration and Units to Remaining.' Uncheck the setting 'Link Budget and At Completion for Not Started Activities.'

Leave the settings 'Link Budget and At Completion for Not Started Activities' and 'Reset Remaining Duration and Units to Original' turned on, but run the import twice: once to add the new assignment, and again to update the Remaining Units/Time. My Oracle Support (Doc ID 1264122.1)