P6blogger
Advice, Tools, and Suggestions on P6 EPPM, Pro, and Oracle Primavera Cloud
Pages
Home
P6 Jobs (Under Construction)
P6 Books
Links to P6 Resources
P6 Instructional Videos
About Me
Tuesday, January 13, 2015
Resources are not able to see the activities.
Check the WBS levels to make sure the “Responsible Manager” is correct and also make sure the status of the WBS is labeled as “Active”. This should change with the project, but may not have.
No comments:
Post a Comment
Newer Post
Older Post
Home
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment