User reports SPI is low.



The assumption is that some time after the baseline was submitted, the planned value cost of this activity was either updated or added. SPI points to Planned Value Cost. Planned Value cost pulls in baseline data. The current baseline seems to not include the planned value cost of initiation. Re-baselining would pull in all data that is currently in the project and the SPI would calculate correctly.