The assumption is that some time after the baseline was submitted, the
planned value cost of this activity was either updated or added. SPI points to
Planned Value Cost. Planned Value cost pulls in baseline data. The current
baseline seems to not include the planned value cost of initiation.
Re-baselining would pull in all data that is currently in the project and the
SPI would calculate correctly.