Copy old project
from EPS Node to What-If section. Choose what project data will be carried
over. If there are budgeted and actual hours for resources, that data should
not be carried over to the new project as the new project start dates will most
likely be in the future. After project
has been copied user can modify the data (project dates, activity dates, WBS
codes, activity codes, resources, etc). After all changes have been made to the
project in the what-if status, create a new project shell in the appropriate node
and copy the WBS & activities from the what-if project to the new project.
Note*** - you can change WBS and project codes
in the active section, but you can only change activity codes in the what-if
section.