CPI and SPI will calculate when an activity has been added, baselined, progressed, and then scheduled. One actuals and duration are showing to start progressing (through updating and scheduling) CPI and SPI will start to calculate. Activity does not need to be marked finished. CPI and SPI can change throughout the life of the activity.