Another suggestion for how to better administer this WBS Summary activity would be to change the activity percent complete type to “physical”. This will allow you to manually enter the progress of the activity. Physical percent complete is commonly used for WBS Summary activities. Below is sample project with the changes we discussed as well as making the activity percent complete physical.
Percent Complete Type
Set the percent complete type to "Duration" for activities which are duration driven, for example, administration tasks and training classes. Set the percent complete type to "Physical" for activities which are work-product driven, for example, creating a document or a product. Set the percent complete type to "Units" for activities which are work effort driven, for example, providing a consulting service (rarely used).
No comments:
Post a Comment