BAC pulls in all the baselined
costs. As for BTC, I want to suggest you are looking at these amounts in the
activities. I thought you were viewing these figures in the project view; which
I don’t think is possible. And yes, when you are changing a resource’s budgeted
hours, that will have an effect on the BTC and yes, you would want to change
the resource’s budgeted hours which would update the activity’s BTC before you
baseline or re-baseline.