User’s dates are not moving and it may be related to how project is being scheduled.
When you schedule, you have three options to choose from. When you choose Retained Logic, the remaining duration of a progressed activity is not scheduled until all predecessors are complete. When you choose Progress Override, network logic is ignored and the activity can progress without delay. When you choose Actual Dates, backward and forward passes are scheduled using actual dates.