Wednesday, March 18, 2015
A contractor has given me a "change log" What are someof the factors I should consider when reviewing the "Change Log"?
Review the contractors hours/costs from before and after the change. If the contractor's activities were already loaded in the schedule, you may want to review what is there now and what is being changed. If you took a baseline of the schedule with the resource loaded activity, you can change the activity's attributes, take another baseline and compare.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment